San Francisco’s bridge authority is lastly transferring ahead to amend the Golden Gate’s noisy new function | Information

anchor

Image courtesy of Wikimedia Commons user Octagon

The insane buzz of the safety slats on the pedestrian handrails of the Golden Gate Bridge is finally being silenced following a recent proposal from the Bridge District.

The fix – developed and tested by bridge engineers in consultation with aerodynamics and acoustics experts – provides for U-shaped clips with a thin rubber sleeve to be attached to all 12,000 vertical battens of the railing. – The San Francisco Chronicle

The haunted acoustic hum is the direct result of a $ 12 million wind retrofit project created by the Golden Gate Bridge Highway and Transportation District. A few enterprising locals made the most of the deafening noise, although the majority of motorists in the Bay Area were vocal about it, which led to the change.

The newly approved upgrades will install a series of sound-absorbing rubber clips along the bridge’s pedestrian walkway, which the San Francisco Chronicle says can mitigate the impact of the larger wind safety louvers by up to 75%. The cost is approximately $ 450,000 and will be fully installed by the end of next year provided there are no major delays.

“It’s a tricky business. We want to be absolutely sure that we are doing it right, ”said bridge spokesman Paolo Cosulich-Schwartz to the Chronicle in May. “We will never sacrifice the structural integrity of the bridge, but we want to be responsive to our neighbors.”